M/S Megastar: Port-Side Hull Cleaning, Rust Treatment & Repaint

Tallinn Old City Harbour, Quay No. 3 · 29 September to 2 October 2025

On site at Quay No. 3: cleaning and coating work underway on Megastar’s port side
M/S Megastar port-side hull before treatment
ProjectPort-side hull cleaning, rust treatment and two-layer repaint
ClientTallink Grupp AS
ContractorAK Marine (ARN OÜ)
VesselM/S Megastar (IMO 9773064)
LocationTallinn Old City Harbour, Quay No. 3
Period29 September to 2 October 2025
Treated area758 m² of a 1,083 m² hull side

The Project

Megastar runs Tallink’s high-frequency Tallinn to Helsinki shuttle. Taking her port side back to a clean, properly protected finish meant pulling her out of service for four days, a rare break in her schedule and a hard deadline to work to.

AK Marine planned the whole job around that fixed window: 29 September at 11:00 to 2 October at 20:00, alongside Quay No. 3 in Tallinn’s Old City Harbour. Cleaning, rust treatment and both paint layers all had to be finished and signed off before she sailed again.

Rust and paint damage on Megastar
Before
Megastar back in service after hull repaint
After

Scope & Method

Chemicals and paint were supplied by the vessel and applied to Tallink’s own specification, so the work turned on preparation quality, sequencing and sign-off rather than materials selection.

Surface preparation

The treated area was stripped of all loose paint with a high-pressure water jet. Remaining paint edges and rust spots were then treated mechanically and smoothed, and all loose paint and cleaning residues were collected as work progressed.

Rust treatment

Rust-damaged sections were treated both mechanically and chemically. Every treated surface was presented to the vessel’s representative for approval before any painting began.

Coating

Cleaned surfaces were treated with the vessel’s chemical, then coated with primer and a first paint layer to the vessel’s paint specification, followed by a second layer for 100% coverage of the treated area.

Boom lifts working along Megastar
Boom lifts positioned along the port-side hull during cleaning and rust treatment

Crew & equipment

AK Marine supplied the labor, tools and lifting equipment for the full window. The vessel provided the electrical and water supply for the lifting equipment and pressure washers, and all work was carried out under a strict permit-to-work system.

Delivered in a Four-Day Window

Planning a job like this is never entirely predictable. Given the dates and the season in Estonia, AK Marine kept the window on track with round-the-clock rotational shifts, working straight through from the first wash to the final coat.

AK Marine crew treating Megastar
During
Cherry pickers alongside Megastar during the works
During
Work focusStatus
Port-side hull cleaning (1,083 m² total, 758 m² treated)Completed
Mechanical and chemical rust treatmentCompleted
Primer and two-layer paint applicationCompleted
Crew mobilisation and demobilisation, Quay No. 3Completed
Surface approvals by the vessel’s representativeSigned off at each stage
The full treated area, 758 square metres of the port-side hull, was cleaned, rust-treated and repainted inside the window, with the vessel’s representative checking and approving the work at every stage.